Houghton Road Corridor Improvements

The Houghton Road Corridor, spanning 13 miles from Interstate 10 to Tanque Verde Road, is one of the corridor projects included in the 2006 voter-approved Regional Transportation Authority (RTA) plan. Six segments have been completed, and others are in progress. A map of the corridor with the schedule for each segment can be viewed below.

Click on a segment to view its individual web page for more detailed information.

Virtual public meetings to review revised public art concepts for the
Houghton Road: 22nd Street to Irvington Road project area were held on Thursday, Sept. 23, 2021.
To view information about the meetings, please
click here.

22nd Street to Irvington Road

Design on this section of Houghton Road began in October 2016. 

Learn More →

Public Art

The Mare and Foal sculpture represents the significant presence of horses in the nearby area, and reflects neighborhood input on the public art.

Learn More →

Valencia to Mary Ann Cleveland Way

Construction on this section of Houghton Road started in September 2020 and was completed in early 2022.

Learn More →

Map of project with stages of completion

Implementation Plan and Schedule


Project Design Status Anticipated
Construction Start
Construction Status
PHASE 1 - DESIGN
7
22nd St. to Irvington Rd.
Complete 2026 TBD
8
Tanque Verde Rd. to Speedway Blvd.
TBD TBD TBD
PHASE 2 - CONSTRUCTION

COMPLETED
1
Old Vail Rd./Mary Ann Cleveland Way Intersection
Complete 2009 Complete
2
Irvington Rd. to Valencia Rd.
Complete 2012 Complete
3
Broadway Blvd. to 22nd St.
Complete 2013 Complete
4
Houghton Bridge over the UPRR
Complete 2017 Complete
5
Union Pacific Railroad to I-10
Complete 2018 Complete
6
Valencia Rd. to Mary Ann Cleveland Way
Complete 2020 Complete

For information on the Mary Ann Cleveland Way Shared-Use Path, click here.

The Chuck Huckelberry Loop website information can be accessed here.


What can we look forward to?